S1: Flexible budget is prepared for a single level of activity. S2: Flexible budget is prepared for a range of activity levels. Which statement(s) is/are correct? MCQ with Answer and Explanation
S1: Flexible budget is prepared for a single level of activity. S2: Flexible budget is prepared for a range of activity levels. Which statement(s) is/are correct?
A. S1 only
B. Neither S1 nor S2
C. S2 only
D. Both S1 and S2
Answer: Option C
Solution (By JKExamLibrary)
A Fixed Budget is prepared for a single, predetermined level of activity. A Flexible Budget is designed to change with the level of activity and is prepared for a range of activity levels. S1 is incorrect, S2 is correct.