12 men can complete a piece of work in 36 days. In how many days will 18 men complete the same work? MCQ with Answer and Explanation

12 men can complete a piece of work in 36 days. In how many days will 18 men complete the same work?
A. 30 days
B. 28 days
C. 18 days
D. 24 days
Answer: Option D
Solution (By JKExamLibrary)
Using M1 * D1 = M2 * D2: 12 * 36 = 18 * D2 => D2 = (12 * 36) / 18 = 12 * 2 = 24 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can complete a work in 13 days and B in 28 days. If they work together, the work will be completed in:
A. 18.88
B. 8.88
C. 13.88
D. 23.88

Correct Answer: Option B


Explanation:
Combined rate = 1/13 + 1/28. Required time = 8.88 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a work in 17 days and B in 34 days. After working together for 5 days, what percentage of work remains?
A. 60.88
B. 55.88
C. 63.38
D. 58.38

Correct Answer: Option B


Explanation:
Remaining work = (1 - 5*(1/17+1/34))×100 = 55.88%.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can complete a work in 19 days and B can complete the same work in 24 days. If they work together, in how many days will the work be completed?
A. 12.6
B. 14.6
C. 10.6
D. 16.6

Correct Answer: Option C


Explanation:
Combined rate = 1/19 + 1/24. Time = 1 ÷ combined rate = 10.6 days.

This question belongs to: Maths Time and Work