14 men can complete a work in 12 days. If 18 men work at the same rate, in how many days will the work be completed? MCQ with Answer and Explanation

14 men can complete a work in 12 days. If 18 men work at the same rate, in how many days will the work be completed?
A. 13.33
B. 11.33
C. 15.33
D. 9.33
Answer: Option D
Solution (By JKExamLibrary)
Total work = 14 × 12 = 168 man-days. Required days = 168/18 = 9.33 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can complete a work in 22 days and B can complete the same work in 32 days. If they work together, in how many days will the work be completed?
A. 17.04
B. 15.04
C. 13.04
D. 19.04

Correct Answer: Option C


Explanation:
Combined rate = 1/22 + 1/32. Time = 1 ÷ combined rate = 13.04 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A, B and C can complete a piece of work in 10, 12 and 15 days respectively. They started together but A left 2 days after the start and B left 3 days before the completion of the work. How long did the work last?
A. 5 days
B. 7 days
C. 6 days
D. 8 days

Correct Answer: Option B


Explanation:
Total work = LCM(10, 12, 15) = 60 units. Efficiency of A = 6, B = 5, C = 4. Let total days be x. A works for 2 days. B works for (x - 3) days. C works for x days. Total work = 2*6 + (x - 3)*5 + 4*x = 60 => 12 + 5x - 15 + 4x = 60 => 9x - 3 = 60 => 9x = 63 => x = 7 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can complete a work in 20 days and B can complete the same work in 15 days. If they work together, in how many days will the work be completed?
A. 10.57
B. 8.57
C. 12.57
D. 14.57

Correct Answer: Option B


Explanation:
Combined rate = 1/20 + 1/15. Time = 1 ÷ combined rate = 8.57 days.

This question belongs to: Maths Time and Work