A, B and C can complete a piece of work in 10, 12 and 15 days respectively. They started together but A left 2 days after the start and B left 3 days before the completion of the work. How long did the work last?
Explanation:
Total work = LCM(10, 12, 15) = 60 units. Efficiency of A = 6, B = 5, C = 4. Let total days be x. A works for 2 days. B works for (x - 3) days. C works for x days. Total work = 2*6 + (x - 3)*5 + 4*x = 60 => 12 + 5x - 15 + 4x = 60 => 9x - 3 = 60 => 9x = 63 => x = 7 days.