15 men can complete a work in 23 days. If 23 men work at the same rate, how many days are required? MCQ with Answer and Explanation

15 men can complete a work in 23 days. If 23 men work at the same rate, how many days are required?
A. 17.5
B. 22.5
C. 20.0
D. 15.0
Answer: Option D
Solution (By JKExamLibrary)
Total work = 345 man-days. Days = 15.0.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can complete a work in 22 days and B can complete the same work in 27 days. If they work together, in how many days will the work be completed?
A. 18.12
B. 16.12
C. 12.12
D. 14.12

Correct Answer: Option C


Explanation:
Combined rate = 1/22 + 1/27. Time = 1 ÷ combined rate = 12.12 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A is twice as fast as B and B is thrice as fast as C. If C alone can complete the work in 24 days, in how many days can they together finish the work?
A. 3 days
B. 2.4 days
C. 4 days
D. 2.6 days

Correct Answer: Option B


Explanation:
Let efficiency of C = 1. Then efficiency of B = 3 * 1 = 3. Efficiency of A = 2 * 3 = 6. Total work = Efficiency of C * Time of C = 1 * 24 = 24 units. Combined efficiency of A, B and C = 6 + 3 + 1 = 10. Time taken together = 24 / 10 = 2.4 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can complete a work in 24 days and B can complete the same work in 19 days. If they work together, in how many days will the work be completed?
A. 14.6
B. 16.6
C. 10.6
D. 12.6

Correct Answer: Option C


Explanation:
Combined rate = 1/24 + 1/19. Time = 1 ÷ combined rate = 10.6 days.