16 men can complete a work in 14 days. If 20 men work at the same rate, in how many days will the work be completed? MCQ with Answer and Explanation

16 men can complete a work in 14 days. If 20 men work at the same rate, in how many days will the work be completed?
A. 11.2
B. 15.2
C. 17.2
D. 13.2
Answer: Option A
Solution (By JKExamLibrary)
Total work = 16 × 14 = 224 man-days. Required days = 224/20 = 11.2 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A is 50% more efficient than B. If A can complete a piece of work in 12 days, in how many days can B complete the same work?
A. 24 days
B. 18 days
C. 20 days
D. 15 days

Correct Answer: Option B


Explanation:
Let efficiency of B = 2, then efficiency of A = 3. Total work = Efficiency of A * Time of A = 3 * 12 = 36 units. Time taken by B = 36 / 2 = 18 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can do a work in 13 days and B in 23 days. In how many days will they complete 75% of the work together?
A. 6.23
B. 8.73
C. 13.73
D. 11.23

Correct Answer: Option A


Explanation:
Combined time for full work multiplied by 0.75 = 6.23 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
X can do a piece of work in 24 days. When he had worked for 4 days, Y joined him. If complete work was finished in 14 days, Y alone can finish that work in:
A. 24 days
B. 18 days
C. 20 days
D. 30 days

Correct Answer: Option A


Explanation:
Let total work be 24 units. Efficiency of X = 1 unit/day. X worked for all 14 days, so work done by X = 14 * 1 = 14 units. Remaining work = 24 - 14 = 10 units. This 10 units of work was done by Y. Y worked for 14 - 4 = 10 days. So Y's efficiency = 10 / 10 = 1 unit/day. Time taken by Y alone = 24 / 1 = 24 days.

This question belongs to: Maths Time and Work