17 men can complete a work in 15 days. If 21 men work at the same rate, in how many days will the work be completed? MCQ with Answer and Explanation

17 men can complete a work in 15 days. If 21 men work at the same rate, in how many days will the work be completed?
A. 14.14
B. 16.14
C. 18.14
D. 12.14
Answer: Option D
Solution (By JKExamLibrary)
Total work = 17 × 15 = 255 man-days. Required days = 255/21 = 12.14 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A, B and C can do a piece of work in 24, 30 and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
A. 11 days
B. 14 days
C. 12 days
D. 13 days

Correct Answer: Option A


Explanation:
Total work = LCM(24, 30, 40) = 120 units. Efficiencies: A = 5, B = 4, C = 3. Total efficiency = 12 units/day. Since C left 4 days before completion, add the work C would have done in those 4 days: 120 + (3 * 4) = 132 units. Total days = 132 / 12 = 11 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B leaves. The days taken by A to finish the remaining work is:
A. 1 day
B. 2 days
C. 3 days
D. 4 days

Correct Answer: Option C


Explanation:
Total work = LCM(12, 15) = 60 units. Efficiency of A = 5, B = 4. In 5 days, work done = 5 * (5 + 4) = 45 units. Remaining work = 60 - 45 = 15 units. Time taken by A to finish remaining work = 15 / 5 = 3 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can complete a work in 33 days and B in 43 days. If both work together, in how many days will the work be completed?
A. 21.17
B. 23.67
C. 26.17
D. 18.67

Correct Answer: Option D


Explanation:
Combined rate = 1/33 + 1/43. Time = 18.67 days.

This question belongs to: Maths Time and Work