17 men can complete a work in 20 days. If 25 men work at the same rate, how many days are required? MCQ with Answer and Explanation

17 men can complete a work in 20 days. If 25 men work at the same rate, how many days are required?
A. 18.6
B. 16.1
C. 13.6
D. 21.1
Answer: Option C
Solution (By JKExamLibrary)
Total work = 340 man-days. Days = 13.6.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
19 men can complete a work in 29 days. If 23 men work at the same rate, in how many days will the work be completed?
A. 29.96
B. 23.96
C. 25.96
D. 27.96

Correct Answer: Option B


Explanation:
Total work = 19 × 29 = 551 man-days. Required days = 551/23 = 23.96 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A and B can complete a piece of work in 24 days and 30 days respectively. Working together, what fraction of the work can they complete in 4 days?
A. 4/15
B. 1/5
C. 7/20
D. 3/10

Correct Answer: Option D


Explanation:
Total work = LCM(24, 30) = 120 units. Efficiency of A = 5, B = 4. Combined efficiency = 9 units/day. In 4 days, work completed = 4 * 9 = 36 units. Fraction of work completed = 36 / 120 = 3 / 10.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can complete a work in 23 days and B can complete the same work in 28 days. If they work together, in how many days will the work be completed?
A. 16.63
B. 14.63
C. 12.63
D. 18.63

Correct Answer: Option C


Explanation:
Combined rate = 1/23 + 1/28. Time = 1 ÷ combined rate = 12.63 days.

This question belongs to: Maths Time and Work