18 men can complete a work in 30 days. If 23 men work at the same rate, the work will be completed in: MCQ with Answer and Explanation

18 men can complete a work in 30 days. If 23 men work at the same rate, the work will be completed in:
A. 38.48
B. 33.48
C. 28.48
D. 23.48
Answer: Option D
Solution (By JKExamLibrary)
Total work = 540 man-days. Time = 540/23 = 23.48 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
13 men can complete a work in 29 days. If 17 men work at the same rate, in how many days will the work be completed?
A. 28.18
B. 24.18
C. 22.18
D. 26.18

Correct Answer: Option C


Explanation:
Total work = 13 × 29 = 377 man-days. Required days = 377/17 = 22.18 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A, B and C can complete a piece of work in 10, 12 and 15 days respectively. They started the work together, but A left after 2 days and B left 3 days before the completion of the work. Find the total duration of the work.
A. 8 days
B. 9 days
C. 7 days
D. 6 days

Correct Answer: Option C


Explanation:
Total work = LCM(10, 12, 15) = 60 units. Efficiency of A = 6, B = 5, C = 4. Let the work last for x days. A works for 2 days: work = 12 units. B works for (x - 3) days: work = 5(x - 3). C works for x days: work = 4x. Total work = 12 + 5x - 15 + 4x = 60 => 9x - 3 = 60 => 9x = 63 => x = 7 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can complete a work in 30 days. What percentage of work will A complete in 6 days?
A. 20.0
B. 30.0
C. 35.0
D. 25.0

Correct Answer: Option A


Explanation:
Percentage completed = (6/30) × 100 = 20.0%.

This question belongs to: Maths Time and Work