21 men can complete a work in 18 days. If 26 men work at the same rate, the work will be completed in: MCQ with Answer and Explanation

21 men can complete a work in 18 days. If 26 men work at the same rate, the work will be completed in:
A. 14.54
B. 24.54
C. 19.54
D. 29.54
Answer: Option A
Solution (By JKExamLibrary)
Total work = 378 man-days. Time = 378/26 = 14.54 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can complete a work in 22 days and B can complete the same work in 22 days. If they work together, in how many days will the work be completed?
A. 15.0
B. 13.0
C. 17.0
D. 11.0

Correct Answer: Option D


Explanation:
Combined rate = 1/22 + 1/22. Time = 1 ÷ combined rate = 11.0 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a project in 20 days and B in 30 days. If they work on alternate days starting with A, in how many days will the project be completed?
A. 22 days
B. 24 days
C. 25 days
D. 26 days

Correct Answer: Option B


Explanation:
Total work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. In a 2-day cycle (A then B), work completed = 3 + 2 = 5 units. Number of cycles required = 60 / 5 = 12 cycles. Total time = 12 * 2 = 24 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
If 10 men can complete a project in 12 days, how many more men are required to finish it in 8 days?
A. 8
B. 6
C. 5
D. 4

Correct Answer: Option C


Explanation:
Using M1 * D1 = M2 * D2: 10 * 12 = M2 * 8 => 120 = 8 * M2 => M2 = 15 men. More men required = 15 - 10 = 5.

This question belongs to: Maths Time and Work