23 men can complete a work in 30 days. If 28 men work at the same rate, the work will be completed in: MCQ with Answer and Explanation

23 men can complete a work in 30 days. If 28 men work at the same rate, the work will be completed in:
A. 24.64
B. 29.64
C. 39.64
D. 34.64
Answer: Option A
Solution (By JKExamLibrary)
Total work = 690 man-days. Time = 690/28 = 24.64 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A and B work together. A alone can complete the work in 18 days and B alone in 34 days. What percentage of the total daily work is contributed by A?
A. 67.88
B. 65.38
C. 72.88
D. 70.38

Correct Answer: Option B


Explanation:
A share = (1/18) / (1/18+1/34) ×100 = 65.38%.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a work in 31 days and B in 31 days. If both work together, in how many days will the work be completed?
A. 23.0
B. 15.5
C. 18.0
D. 20.5

Correct Answer: Option B


Explanation:
Combined rate = 1/31 + 1/31. Time = 15.5 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
15 men can complete a work in 25 days. If 19 men work at the same rate, in how many days will the work be completed?
A. 25.74
B. 21.74
C. 19.74
D. 23.74

Correct Answer: Option C


Explanation:
Total work = 15 × 25 = 375 man-days. Required days = 375/19 = 19.74 days.

This question belongs to: Maths Time and Work