8 men can complete a work in 18 days. If 12 men work at the same rate, in how many days will the work be completed? MCQ with Answer and Explanation

8 men can complete a work in 18 days. If 12 men work at the same rate, in how many days will the work be completed?
A. 18.0
B. 14.0
C. 16.0
D. 12.0
Answer: Option D
Solution (By JKExamLibrary)
Total work = 8 × 18 = 144 man-days. Required days = 144/12 = 12.0 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can finish a work in 18 days and B can do the same work in half the time taken by A. Then, working together, what part of the same work can they finish in a day?
A. 1/6
B. 1/4
C. 2/5
D. 1/9

Correct Answer: Option A


Explanation:
Time taken by A = 18 days, so B takes 9 days. Efficiency of A = 1/18, B = 1/9. Together in one day = 1/18 + 1/9 = 3/18 = 1/6.

This question belongs to: Maths Time and Work
Question #2 Report Error
14 men can complete a work in 24 days. If 18 men work at the same rate, in how many days will the work be completed?
A. 22.67
B. 18.67
C. 20.67
D. 24.67

Correct Answer: Option B


Explanation:
Total work = 14 × 24 = 336 man-days. Required days = 336/18 = 18.67 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can do a work in 18 days and B in 24 days. They start together but A leaves 3 days before the completion of the work. Find the total number of days taken to complete the work.
A. 12 days
B. 11 days
C. 13 days
D. 10 days

Correct Answer: Option A


Explanation:
Total work = LCM(18, 24) = 72 units. Efficiency of A = 4, B = 3. Let total days be x. A works for (x - 3) days, B works for x days. 4(x - 3) + 3x = 72 => 4x - 12 + 3x = 72 => 7x = 84 => x = 12 days.

This question belongs to: Maths Time and Work