9 men can complete a work in 19 days. If 13 men work at the same rate, in how many days will the work be completed? MCQ with Answer and Explanation

9 men can complete a work in 19 days. If 13 men work at the same rate, in how many days will the work be completed?
A. 13.15
B. 17.15
C. 19.15
D. 15.15
Answer: Option A
Solution (By JKExamLibrary)
Total work = 9 × 19 = 171 man-days. Required days = 171/13 = 13.15 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
10 men can complete a piece of work in 15 days and 15 women can complete the same work in 12 days. If all the 10 men and 15 women work together, in how many days will the work be completed?
A. 6(2/3) days
B. 7 days
C. 6(1/3) days
D. 8 days

Correct Answer: Option A


Explanation:
1-day work of 10 men = 1/15. 1-day work of 15 women = 1/12. Combined 1-day work = 1/15 + 1/12 = (4 + 5) / 60 = 9 / 60 = 3 / 20. Total days required = 20 / 3 = 6(2/3) days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A is twice as good a workman as B and together they finish a piece of work in 18 days. In how many days will A alone finish the work?
A. 36 days
B. 27 days
C. 54 days
D. 45 days

Correct Answer: Option B


Explanation:
Ratio of work done by A and B = 2:1. Let B's 1-day work be x, so A's 1-day work is 2x. Together, 3x = 1/18, which means x = 1/54. A's 1-day work = 2 * (1/54) = 1/27. Thus, A alone completes it in 27 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
16 men can complete a work in 20 days. If 20 men work at the same rate, in how many days will the work be completed?
A. 22.0
B. 20.0
C. 16.0
D. 18.0

Correct Answer: Option C


Explanation:
Total work = 16 × 20 = 320 man-days. Required days = 320/20 = 16.0 days.

This question belongs to: Maths Time and Work