A and B can complete a work in 15 days and 10 days respectively. They started the work together but B left after 2 days. In how many days will A complete the remaining work? MCQ with Answer and Explanation

A and B can complete a work in 15 days and 10 days respectively. They started the work together but B left after 2 days. In how many days will A complete the remaining work?
A. 8 days
B. 10 days
C. 9 days
D. 11 days
Answer: Option B
Solution (By JKExamLibrary)
Total work = LCM(15, 10) = 30 units. Efficiency of A = 2, B = 3. Combined efficiency = 5 units/day. In 2 days, work completed = 2 * 5 = 10 units. Remaining work = 30 - 10 = 20 units. Time taken by A to complete remaining work = 20 / 2 = 10 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A and B work together. A alone can complete the work in 24 days and B alone in 26 days. What percentage of the total daily work is contributed by A?
A. 57.0
B. 59.5
C. 52.0
D. 54.5

Correct Answer: Option C


Explanation:
A share = (1/24) / (1/24+1/26) ×100 = 52.0%.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can do a work in 18 days and B in 24 days. They start together but A leaves 3 days before the completion of the work. Find the total number of days taken to complete the work.
A. 10 days
B. 11 days
C. 13 days
D. 12 days

Correct Answer: Option D


Explanation:
Total work = LCM(18, 24) = 72 units. Efficiency of A = 4, B = 3. Let total days be x. A works for (x - 3) days, B works for x days. 4(x - 3) + 3x = 72 => 4x - 12 + 3x = 72 => 7x = 84 => x = 12 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A is twice as fast as B and B is twice as fast as C. If they together can complete a work in 4 days, in how many days can C alone complete it?
A. 24 days
B. 28 days
C. 32 days
D. 16 days

Correct Answer: Option B


Explanation:
Let efficiency of C = 1, then B = 2 and A = 4. Combined efficiency = 1 + 2 + 4 = 7 units/day. Total work = 4 * 7 = 28 units. Time taken by C alone = 28 / 1 = 28 days.

This question belongs to: Maths Time and Work