A and B can complete a work in 15 days and 10 days respectively. They started the work together but B left after 2 days. In how many days will A complete the remaining work? MCQ with Answer and Explanation
A and B can complete a work in 15 days and 10 days respectively. They started the work together but B left after 2 days. In how many days will A complete the remaining work?
A. 8 days
B. 10 days
C. 9 days
D. 11 days
Answer: Option B
Solution (By JKExamLibrary)
Total work = LCM(15, 10) = 30 units. Efficiency of A = 2, B = 3. Combined efficiency = 5 units/day. In 2 days, work completed = 2 * 5 = 10 units. Remaining work = 30 - 10 = 20 units. Time taken by A to complete remaining work = 20 / 2 = 10 days.
A can do a work in 18 days and B in 24 days. They start together but A leaves 3 days before the completion of the work. Find the total number of days taken to complete the work.
Explanation:
Total work = LCM(18, 24) = 72 units. Efficiency of A = 4, B = 3. Let total days be x. A works for (x - 3) days, B works for x days. 4(x - 3) + 3x = 72 => 4x - 12 + 3x = 72 => 7x = 84 => x = 12 days.
Explanation:
Let efficiency of C = 1, then B = 2 and A = 4. Combined efficiency = 1 + 2 + 4 = 7 units/day. Total work = 4 * 7 = 28 units. Time taken by C alone = 28 / 1 = 28 days.
No comments yet. Be the first to start the discussion!