A and B can complete a work together in 15 days. They work together for 3 days, then A leaves. If B alone completes the remaining work in 16 days, in how many days can A alone complete the whole work? MCQ with Answer and Explanation

A and B can complete a work together in 15 days. They work together for 3 days, then A leaves. If B alone completes the remaining work in 16 days, in how many days can A alone complete the whole work?
A. 45 days
B. 75 days
C. 30 days
D. 60 days
Answer: Option D
Solution (By JKExamLibrary)
Let the total work be 60 units. Combined efficiency of A and B = 60 / 15 = 4 units/day. In 3 days, they complete 3 * 4 = 12 units. Remaining work = 60 - 12 = 48 units. B completes 48 units in 16 days, so B's efficiency = 48 / 16 = 3 units/day. A's efficiency = 4 - 3 = 1 unit/day. Time taken by A alone = 60 / 1 = 60 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can complete a work in 19 days and B in 19 days. If both work together, in how many days will the work be completed?
A. 12.0
B. 9.5
C. 17.0
D. 14.5

Correct Answer: Option B


Explanation:
Combined rate = 1/19 + 1/19. Time = 9.5 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a work in 12 days and B can complete the same work in 32 days. If they work together, in how many days will the work be completed?
A. 10.73
B. 8.73
C. 14.73
D. 12.73

Correct Answer: Option B


Explanation:
Combined rate = 1/12 + 1/32. Time = 1 ÷ combined rate = 8.73 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can complete a work in 23 days and B can complete the same work in 18 days. If they work together, in how many days will the work be completed?
A. 10.1
B. 14.1
C. 12.1
D. 16.1

Correct Answer: Option A


Explanation:
Combined rate = 1/23 + 1/18. Time = 1 ÷ combined rate = 10.1 days.

This question belongs to: Maths Time and Work