A and B together can do a piece of work in 6 days. If A alone can do it in 18 days, in how many days can B alone complete the work? MCQ with Answer and Explanation

A and B together can do a piece of work in 6 days. If A alone can do it in 18 days, in how many days can B alone complete the work?
A. 12 days
B. 15 days
C. 20 days
D. 9 days
Answer: Option D
Solution (By JKExamLibrary)
Combined 1-day work = 1/6. A's 1-day work = 1/18. B's 1-day work = 1/6 - 1/18 = 2/18 = 1/9. Therefore, B alone can complete the work in 9 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can complete a piece of work in 18 days, B in 24 days and C in 36 days. If they work together, in how many days will they finish the work?
A. 6 days
B. 8 days
C. 9 days
D. 7 days

Correct Answer: Option B


Explanation:
Total work = LCM(18, 24, 36) = 72 units. Efficiency of A = 4, B = 3, C = 2. Combined efficiency = 4 + 3 + 2 = 9 units/day. Time taken together = 72 / 9 = 8 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A, B and C can complete a work in 10, 12 and 15 days respectively. They start working together. Find the number of days required to complete the work.
A. 3 days
B. 4 days
C. 6 days
D. 5 days

Correct Answer: Option B


Explanation:
Total work = LCM(10, 12, 15) = 60 units. Efficiency of A = 6, B = 5, C = 4. Combined efficiency = 6 + 5 + 4 = 15 units/day. Time taken = 60 / 15 = 4 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can complete a work in 25 days and B in 25 days. If both work together, in how many days will the work be completed?
A. 15.0
B. 17.5
C. 20.0
D. 12.5

Correct Answer: Option D


Explanation:
Combined rate = 1/25 + 1/25. Time = 12.5 days.

This question belongs to: Maths Time and Work