A, B and C can do a piece of work in 24, 30 and 40 days respectively. They start together but C leaves 4 days before the completion of the work. In how many days was the work completed? MCQ with Answer and Explanation
A, B and C can do a piece of work in 24, 30 and 40 days respectively. They start together but C leaves 4 days before the completion of the work. In how many days was the work completed?
A. 10 days
B. 11 days
C. 13 days
D. 12 days
Answer: Option B
Solution (By JKExamLibrary)
Total work = LCM(24, 30, 40) = 120 units. Efficiency of A = 5, B = 4, C = 3. Let the total number of days be x. A and B work for x days, while C works for (x - 4) days. 5x + 4x + 3(x - 4) = 120 => 12x - 12 = 120 => 12x = 132 => x = 11 days.
Explanation:
10 Men = 20 Women => 1 Man = 2 Women. 24 men + 17 women = 24 * 2 + 17 = 48 + 17 = 65 women. Since 20 women do the work in 13 days, 65 women will do it in (20 * 13) / 65 = 260 / 65 = 4 days.
Explanation:
Let efficiency of B = 1, then efficiency of A = 2. Combined efficiency = 3 units/day. Total work = 8 * 3 = 24 units. Time taken by A alone = 24 / 2 = 12 days.