Correct Answer: Option A
Explanation:
Total work = LCM(20, 30, 60) = 60 units. Efficiency of A = 3, B = 2, C = 1. Day 1: A works (3 units). Day 2: A works (3 units). Day 3: A, B, and C work together (3 + 2 + 1 = 6 units). Total work in 3 days = 3 + 3 + 6 = 12 units. To complete 60 units, number of 3-day cycles needed = 60 / 12 = 5 cycles. Total days = 5 * 3 = 15 days.
This question belongs to:
Maths
Time and Work
No comments yet. Be the first to start the discussion!