A can complete a piece of work in 10 days, B in 15 days, and C in 20 days. A and C worked together for 2 days and then A was replaced by B. In how many days altogether was the work completed? MCQ with Answer and Explanation

A can complete a piece of work in 10 days, B in 15 days, and C in 20 days. A and C worked together for 2 days and then A was replaced by B. In how many days altogether was the work completed?
A. 6 days
B. 9 days
C. 8 days
D. 7 days
Answer: Option C
Solution (By JKExamLibrary)
Total work = LCM(10, 15, 20) = 60 units. Efficiency of A = 6, B = 4, C = 3. A and C work for 2 days: work done = 2 * (6 + 3) = 18 units. Remaining work = 60 - 18 = 42 units. B and C complete remaining work together with efficiency = 4 + 3 = 7 units/day. Time taken for remaining work = 42 / 7 = 6 days. Total time = 2 + 6 = 8 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A is twice as fast as B and B is thrice as fast as C. If C alone can complete the work in 24 days, in how many days can they together finish the work?
A. 2.4 days
B. 4 days
C. 2.6 days
D. 3 days

Correct Answer: Option A


Explanation:
Let efficiency of C = 1. Then efficiency of B = 3 * 1 = 3. Efficiency of A = 2 * 3 = 6. Total work = Efficiency of C * Time of C = 1 * 24 = 24 units. Combined efficiency of A, B and C = 6 + 3 + 1 = 10. Time taken together = 24 / 10 = 2.4 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a work in 25 days and B in 25 days. If both work together, in how many days will the work be completed?
A. 12.5
B. 15.0
C. 20.0
D. 17.5

Correct Answer: Option A


Explanation:
Combined rate = 1/25 + 1/25. Time = 12.5 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A, B and C can do a work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
A. 18 days
B. 12 days
C. 15 days
D. 16 days

Correct Answer: Option C


Explanation:
Total work = LCM(20, 30, 60) = 60 units. Efficiency of A = 3, B = 2, C = 1. Day 1: A works (3 units). Day 2: A works (3 units). Day 3: A, B, and C work together (3 + 2 + 1 = 6 units). Total work in 3 days = 3 + 3 + 6 = 12 units. To complete 60 units, number of 3-day cycles needed = 60 / 12 = 5 cycles. Total days = 5 * 3 = 15 days.

This question belongs to: Maths Time and Work