A can complete a work in 15 days and B can complete the same work in 20 days. If they work together, in how many days will the work be completed? MCQ with Answer and Explanation

A can complete a work in 15 days and B can complete the same work in 20 days. If they work together, in how many days will the work be completed?
A. 10.57
B. 12.57
C. 14.57
D. 8.57
Answer: Option D
Solution (By JKExamLibrary)
Combined rate = 1/15 + 1/20. Time = 1 ÷ combined rate = 8.57 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can complete a work in 16 days and B in 29 days. If they work together, the work will be completed in:
A. 20.31
B. 10.31
C. 15.31
D. 25.31

Correct Answer: Option B


Explanation:
Combined rate = 1/16 + 1/29. Required time = 10.31 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a work in 18 days and B in 24 days. If both work together, in how many days will the work be completed?
A. 10.29
B. 15.29
C. 12.79
D. 17.79

Correct Answer: Option A


Explanation:
Combined rate = 1/18 + 1/24. Time = 10.29 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A and B can do a job in 12 days and 16 days respectively. Both work together for 3 days and then A leaves. How long will B take to complete the remaining work?
A. 10 days
B. 7 days
C. 9 days
D. 8 days

Correct Answer: Option C


Explanation:
Total work = LCM(12, 16) = 48 units. Efficiency of A = 4, B = 3. Combined efficiency = 7 units/day. In 3 days, work completed = 7 * 3 = 21 units. Remaining work = 48 - 21 = 27 units. Time taken by B for remaining work = 27 / 3 = 9 days.

This question belongs to: Maths Time and Work