A can complete a work in 17 days and B in 22 days. If both work together, in how many days will the work be completed? MCQ with Answer and Explanation

A can complete a work in 17 days and B in 22 days. If both work together, in how many days will the work be completed?
A. 17.09
B. 14.59
C. 9.59
D. 12.09
Answer: Option C
Solution (By JKExamLibrary)
Combined rate = 1/17 + 1/22. Time = 9.59 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can complete a piece of work in 14 days and B in 21 days. They begin together but A leaves 3 days before the completion of the work. Find the total number of days taken to complete the work.
A. 9(1/5) days
B. 10(1/5) days
C. 11 days
D. 8(3/5) days

Correct Answer: Option B


Explanation:
Total work = LCM(14, 21) = 42 units. Efficiency of A = 3, B = 2. Let total days be x. A works for (x - 3) days, B works for x days. 3(x - 3) + 2x = 42 => 3x - 9 + 2x = 42 => 5x = 51 => x = 51/5 = 10(1/5) days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a work in 30 days and B in 22 days. If both work together, in how many days will the work be completed?
A. 20.19
B. 12.69
C. 15.19
D. 17.69

Correct Answer: Option B


Explanation:
Combined rate = 1/30 + 1/22. Time = 12.69 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A and B can do a work in 12 days, B and C in 15 days, and C and A in 20 days. How many days will A alone take to finish the work?
A. 40 days
B. 60 days
C. 30 days
D. 20 days

Correct Answer: Option C


Explanation:
Total work = LCM(12, 15, 20) = 60 units. Efficiency of (A+B) = 5, (B+C) = 4, (C+A) = 3. Summing efficiencies gives 2*(A+B+C) = 12 => Efficiency of (A+B+C) = 6 units/day. Efficiency of A = (A+B+C) - (B+C) = 6 - 4 = 2 units/day. Time taken by A alone = 60 / 2 = 30 days.

This question belongs to: Maths Time and Work