A can complete a work in 20 days and B in 25 days. If they work together, the work will be completed in: MCQ with Answer and Explanation

A can complete a work in 20 days and B in 25 days. If they work together, the work will be completed in:
A. 16.11
B. 11.11
C. 26.11
D. 21.11
Answer: Option B
Solution (By JKExamLibrary)
Combined rate = 1/20 + 1/25. Required time = 11.11 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A and B together can do a piece of work in 8 days, B and C together in 12 days, and C and A together in 16 days. In how many days can A, B and C together finish the work?
A. 6(6/13) days
B. 8(2/13) days
C. 5(5/13) days
D. 7(5/13) days

Correct Answer: Option D


Explanation:
Total work = LCM(8, 12, 16) = 48 units. Efficiency of (A+B) = 6, (B+C) = 4, (C+A) = 3. Summing efficiencies gives 2 * (A+B+C) = 13, so efficiency of (A+B+C) = 13/2. Time taken = 48 / (13/2) = 96 / 13 = 7(5/13) days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a work in 16 days and B in 32 days. After working together for 5 days, what percentage of work remains?
A. 60.62
B. 53.12
C. 58.12
D. 55.62

Correct Answer: Option B


Explanation:
Remaining work = (1 - 5*(1/16+1/32))×100 = 53.12%.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can complete a work in 20 days and B in 14 days. If they work together, the work will be completed in:
A. 23.24
B. 13.24
C. 18.24
D. 8.24

Correct Answer: Option D


Explanation:
Combined rate = 1/20 + 1/14. Required time = 8.24 days.

This question belongs to: Maths Time and Work