A can complete a work in 21 days and B in 17 days. If they work together, the work will be completed in: MCQ with Answer and Explanation

A can complete a work in 21 days and B in 17 days. If they work together, the work will be completed in:
A. 9.39
B. 19.39
C. 24.39
D. 14.39
Answer: Option A
Solution (By JKExamLibrary)
Combined rate = 1/21 + 1/17. Required time = 9.39 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A is 40% more efficient than B. If they together can finish a work in 10 days, in how many days can A alone finish it?
A. 14 days
B. 15 days
C. 17(1/7) days
D. 16(2/3) days

Correct Answer: Option C


Explanation:
Let efficiency of B = 5, then efficiency of A = 7. Combined efficiency = 12 units/day. Total work = 10 * 12 = 120 units. Time taken by A alone = 120 / 7 = 17(1/7) days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A group of men decided to do a work in 10 days, but 5 of them became absent. If the rest of the group did the work in 12 days, find the original number of men.
A. 30
B. 25
C. 35
D. 40

Correct Answer: Option A


Explanation:
Let the original number of men be x. Using M1 * D1 = M2 * D2: x * 10 = (x - 5) * 12 => 10x = 12x - 60 => 2x = 60 => x = 30.

This question belongs to: Maths Time and Work
Question #3 Report Error
A and B can do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days. In how many days will A, B, and C finish it working together?
A. 10 days
B. 5 days
C. 8 days
D. 12 days

Correct Answer: Option A


Explanation:
2(A + B + C)'s 1-day work = 1/12 + 1/15 + 1/20 = 12/60 = 1/5. Therefore, (A + B + C)'s 1-day work = 1/10. Working together, they finish in 10 days.

This question belongs to: Maths Time and Work