A can complete a work in 8 days and B in 29 days. If they work together, the work will be completed in: MCQ with Answer and Explanation

A can complete a work in 8 days and B in 29 days. If they work together, the work will be completed in:
A. 11.27
B. 6.27
C. 21.27
D. 16.27
Answer: Option B
Solution (By JKExamLibrary)
Combined rate = 1/8 + 1/29. Required time = 6.27 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A and B can complete a piece of work in 20 days and 30 days respectively. If they work on alternate days starting with B, in how many days will the work be finished?
A. 26 days
B. 23 days
C. 24 days
D. 25 days

Correct Answer: Option C


Explanation:
Total work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. In 2 days (B then A), work completed = 2 + 3 = 5 units. Time taken to complete 60 units = (60 / 5) * 2 = 24 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a work in 17 days and B in 24 days. If they work together, the work will be completed in:
A. 19.95
B. 24.95
C. 9.95
D. 14.95

Correct Answer: Option C


Explanation:
Combined rate = 1/17 + 1/24. Required time = 9.95 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can complete a work in 20 days. What percentage of the work will be completed in 7 days?
A. 35.0
B. 37.5
C. 40.0
D. 42.5

Correct Answer: Option A


Explanation:
Completed percentage = (7/20)×100 = 35.0%.

This question belongs to: Maths Time and Work