A can complete a work in 9 days and B in 16 days. If they work together, the work will be completed in: MCQ with Answer and Explanation

A can complete a work in 9 days and B in 16 days. If they work together, the work will be completed in:
A. 15.76
B. 20.76
C. 10.76
D. 5.76
Answer: Option D
Solution (By JKExamLibrary)
Combined rate = 1/9 + 1/16. Required time = 5.76 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A and B can complete a piece of work in 18 days and 24 days respectively. They worked together for 6 days and then A left. In how many days will B complete the remaining work?
A. 10 days
B. 8 days
C. 14 days
D. 12 days

Correct Answer: Option A


Explanation:
Total work = LCM(18, 24) = 72 units. Efficiency of A = 4, B = 3. Combined efficiency = 7. In 6 days, work done = 6 * 7 = 42 units. Remaining work = 72 - 42 = 30 units. Time taken by B to finish remaining work = 30 / 3 = 10 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
18 men can complete a work in 28 days. If 22 men work at the same rate, in how many days will the work be completed?
A. 22.91
B. 28.91
C. 24.91
D. 26.91

Correct Answer: Option A


Explanation:
Total work = 18 × 28 = 504 man-days. Required days = 504/22 = 22.91 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
17 men can complete a work in 27 days. If 21 men work at the same rate, in how many days will the work be completed?
A. 27.86
B. 25.86
C. 23.86
D. 21.86

Correct Answer: Option D


Explanation:
Total work = 17 × 27 = 459 man-days. Required days = 459/21 = 21.86 days.

This question belongs to: Maths Time and Work