A can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave. Then C alone finishes the remaining work in 10 days. In how many days can C alone finish the full work? MCQ with Answer and Explanation

A can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave. Then C alone finishes the remaining work in 10 days. In how many days can C alone finish the full work?
A. 35 days
B. 30 days
C. 25 days
D. 24 days
Answer: Option D
Solution (By JKExamLibrary)
Total work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. Combined efficiency = 5 units/day. In 7 days, work done = 7 * 5 = 35 units. Remaining work = 60 - 35 = 25 units. C takes 10 days to do 25 units, so efficiency of C = 25 / 10 = 2.5 units/day. Time taken by C for full work = 60 / 2.5 = 24 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
12 men can complete a work in 28 days. If 16 men work at the same rate, in how many days will the work be completed?
A. 27.0
B. 21.0
C. 23.0
D. 25.0

Correct Answer: Option B


Explanation:
Total work = 12 × 28 = 336 man-days. Required days = 336/16 = 21.0 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A, B and C can do a piece of work in 10, 12 and 15 days respectively. They began the work together but A left after 2 days and B left 3 days before the completion of the work. How long did the work last?
A. 7 days
B. 6 days
C. 5 days
D. 8 days

Correct Answer: Option A


Explanation:
Total work = LCM(10, 12, 15) = 60 units. Efficiency of A = 6, B = 5, C = 4. Let the total time be x days. A worked for 2 days. B worked for (x - 3) days. C worked for x days. Total work = 2*6 + (x - 3)*5 + x*4 = 60 => 12 + 5x - 15 + 4x = 60 => 9x - 3 = 60 => 9x = 63 => x = 7 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can complete a work in 20 days and B in 30 days. They start together but A leaves after 4 days. In how many total days will the work be completed?
A. 24 days
B. 20 days
C. 16 days
D. 25 days

Correct Answer: Option A


Explanation:
Total work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. In 4 days, work completed = 4 * (3 + 2) = 20 units. Remaining work = 60 - 20 = 40 units. Time taken by B to finish remaining work = 40 / 2 = 20 days. Total days = 4 + 20 = 24 days.

This question belongs to: Maths Time and Work