A can do a piece of work in 40 days. He works at it for 8 days and then B finishes it in 16 days. How long will A and B together take to complete the work? MCQ with Answer and Explanation

A can do a piece of work in 40 days. He works at it for 8 days and then B finishes it in 16 days. How long will A and B together take to complete the work?
A. 20 days
B. 13(1/3) days
C. 15 days
D. 25 days
Answer: Option B
Solution (By JKExamLibrary)
Let total work be 40 units. Efficiency of A = 1 unit/day. In 8 days, A completes 8 units. Remaining work = 40 - 8 = 32 units. B finishes 32 units in 16 days, so B's efficiency = 32 / 16 = 2 units/day. Combined efficiency of A and B = 1 + 2 = 3 units/day. Time taken together = 40 / 3 = 13(1/3) days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can complete a work in 15 days and B in 26 days. If they work together, the work will be completed in:
A. 24.51
B. 9.51
C. 19.51
D. 14.51

Correct Answer: Option B


Explanation:
Combined rate = 1/15 + 1/26. Required time = 9.51 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a work in 9 days and B in 24 days. If they work together, the work will be completed in:
A. 11.55
B. 16.55
C. 6.55
D. 21.55

Correct Answer: Option C


Explanation:
Combined rate = 1/9 + 1/24. Required time = 6.55 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A is 50% more efficient than B. If A can complete a piece of work in 12 days, in how many days can B complete the same work?
A. 24 days
B. 15 days
C. 20 days
D. 18 days

Correct Answer: Option D


Explanation:
Let efficiency of B = 2, then efficiency of A = 3. Total work = Efficiency of A * Time of A = 3 * 12 = 36 units. Time taken by B = 36 / 2 = 18 days.

This question belongs to: Maths Time and Work