A can finish a work in 12 days and B can do it in 15 days. After A had worked for 3 days, B also joined him to finish the remaining work. In how many days was the remaining work completed? MCQ with Answer and Explanation

A can finish a work in 12 days and B can do it in 15 days. After A had worked for 3 days, B also joined him to finish the remaining work. In how many days was the remaining work completed?
A. 5 days
B. 3 days
C. 4 days
D. 6 days
Answer: Option A
Solution (By JKExamLibrary)
Total work = LCM(12, 15) = 60 units. Efficiency of A = 5, B = 4. In 3 days, A completed 3 * 5 = 15 units. Remaining work = 60 - 15 = 45 units. Combined efficiency of A and B = 5 + 4 = 9 units/day. Time taken for remaining work = 45 / 9 = 5 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can complete a work in 15 days and B in 26 days. If they work together, the work will be completed in:
A. 19.51
B. 9.51
C. 24.51
D. 14.51

Correct Answer: Option B


Explanation:
Combined rate = 1/15 + 1/26. Required time = 9.51 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A and B can do a piece of work in 30 days and 36 days respectively. They began the work together but A left after some days and B finished the remaining work in 25 days. After how many days did A leave?
A. 5 days
B. 8 days
C. 6 days
D. 4 days

Correct Answer: Option A


Explanation:
Total work = LCM(30, 36) = 180 units. Efficiency of A = 6, B = 5. B worked alone for 25 days: work done = 25 * 5 = 125 units. Remaining work = 180 - 125 = 55 units. This was completed by A and B together. Combined efficiency = 11. Days worked together = 55 / 11 = 5 days. Thus, A left after 5 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
16 men can complete a work in 20 days. If 20 men work at the same rate, in how many days will the work be completed?
A. 16.0
B. 22.0
C. 20.0
D. 18.0

Correct Answer: Option A


Explanation:
Total work = 16 × 20 = 320 man-days. Required days = 320/20 = 16.0 days.

This question belongs to: Maths Time and Work