A can finish a work in 15 days and B in 20 days. They work together for 6 days and then B leaves. In how many days will A finish the remaining work? MCQ with Answer and Explanation
A can finish a work in 15 days and B in 20 days. They work together for 6 days and then B leaves. In how many days will A finish the remaining work?
A. 3.5 days
B. 4.5 days
C. 6 days
D. 5 days
Answer: Option B
Solution (By JKExamLibrary)
Total work = LCM(15, 20) = 60 units. Efficiency of A = 4, B = 3. Combined efficiency = 7. In 6 days, work done = 6 * 7 = 42 units. Remaining work = 60 - 42 = 18 units. Time taken by A to complete remaining work = 18 / 4 = 4.5 days.
A and B can do a piece of work in 30 days and 36 days respectively. They began the work together but A left after some days and B finished the remaining work in 25 days. After how many days did A leave?
Explanation:
Total work = LCM(30, 36) = 180 units. Efficiency of A = 6, B = 5. B worked alone for 25 days: work done = 25 * 5 = 125 units. Remaining work = 180 - 125 = 55 units. This was completed by A and B together. Combined efficiency = 11. Days worked together = 55 / 11 = 5 days. Thus, A left after 5 days.
No comments yet. Be the first to start the discussion!