A is 50% more efficient than B. C does half of the work done by A and B together in the same time. If C alone can do the work in 40 days, then A, B and C together can do the work in: MCQ with Answer and Explanation

A is 50% more efficient than B. C does half of the work done by A and B together in the same time. If C alone can do the work in 40 days, then A, B and C together can do the work in:
A. 20 days
B. 15 days
C. 13(1/3) days
D. 30 days
Answer: Option C
Solution (By JKExamLibrary)
Let efficiency of B = 2, then efficiency of A = 3. Combined efficiency of A and B = 5. Efficiency of C = 5 / 2 = 2.5. Total work = Efficiency of C * Time taken by C = 2.5 * 40 = 100 units. Combined efficiency of A, B and C = 3 + 2 + 2.5 = 7.5 units/day. Time taken together = 100 / 7.5 = 1000 / 75 = 40 / 3 = 13(1/3) days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can complete a work in 16 days and B can complete the same work in 26 days. If they work together, in how many days will the work be completed?
A. 9.9
B. 11.9
C. 15.9
D. 13.9

Correct Answer: Option A


Explanation:
Combined rate = 1/16 + 1/26. Time = 1 ÷ combined rate = 9.9 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a work in 33 days and B in 43 days. If both work together, in how many days will the work be completed?
A. 21.17
B. 23.67
C. 18.67
D. 26.17

Correct Answer: Option C


Explanation:
Combined rate = 1/33 + 1/43. Time = 18.67 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can complete a project in 20 days and B in 30 days. If they work on alternate days starting with A, in how many days will the project be completed?
A. 24 days
B. 26 days
C. 22 days
D. 25 days

Correct Answer: Option A


Explanation:
Total work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. In a 2-day cycle (A then B), work completed = 3 + 2 = 5 units. Number of cycles required = 60 / 5 = 12 cycles. Total time = 12 * 2 = 24 days.

This question belongs to: Maths Time and Work