A is twice as fast as B. If B can complete a work in 12 days, in how many days can A and B together complete the work?
A. 4 days
B. 8 days
C. 6 days
D. 3 days
Answer: Option A
Solution (By JKExamLibrary)
B takes 12 days, so A takes 6 days. Total work = 12 units. Efficiency of A = 2, B = 1. Combined efficiency = 3 units/day. Time taken together = 12 / 3 = 4 days.
Explanation:
3 Men = 5 Women => 6 Men = 10 Women. 6 men + 5 women = 10 women + 5 women = 15 women. Since 5 women take 12 days, 15 women will take (5 * 12) / 15 = 60 / 15 = 4 days.
No comments yet. Be the first to start the discussion!