If 15 men can complete a work in 20 days, how many men are required to complete the work in 10 days? MCQ with Answer and Explanation

If 15 men can complete a work in 20 days, how many men are required to complete the work in 10 days?
A. 32
B. 28
C. 25
D. 30
Answer: Option D
Solution (By JKExamLibrary)
M1×D1 = M2×D2 → 15×20 = M2×10 → M2 = 30.

This question belongs to: Maths Percentage

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Percentage Questions

Question #1 Report Error
A man saves 30% of his income. If his income increases by 20% and expenditure increases by 10%, his savings increase by:
A. 33.33%
B. 43.33%
C. 40%
D. 50%

Correct Answer: Option B


Explanation:
Income 100, exp 70, sav 30. New income 120, new exp 70×1.1=77, sav 43. Increase 13, % = (13/30)×100 = 43.33%.

This question belongs to: Maths Percentage
Question #2 Report Error
A number is increased by 15% and then decreased by 15%. If the resulting number is 782, what was the original number?
A. 800
B. 820
C. 780
D. 750

Correct Answer: Option A


Explanation:
1.15 × 0.85 = 0.9775. 0.9775x = 782 → x = 782/0.9775 = 800.

This question belongs to: Maths Percentage
Question #3 Report Error
A person buys an article at 20% discount on the marked price and sells it at the marked price. What is his profit percent?
A. 28%
B. 22%
C. 25%
D. 20%

Correct Answer: Option C


Explanation:
Let MP=100, CP=80, SP=100, profit% = (20/80)×100 = 25%.

This question belongs to: Maths Percentage