A and B together can do a piece of work in 9 days. If A does thrice the work of B in a given time, how many days will A alone take to complete the total work?
Explanation:
Ratio of efficiency of A : B = 3 : 1. Combined efficiency = 3 + 1 = 4. Total work = 9 * 4 = 36 units. Time taken by A alone = 36 / 3 = 12 days.