14 men can complete a work in 18 days. If 18 men work at the same rate, in how many days will the work be completed? MCQ with Answer and Explanation

14 men can complete a work in 18 days. If 18 men work at the same rate, in how many days will the work be completed?
A. 18.0
B. 20.0
C. 14.0
D. 16.0
Answer: Option C
Solution (By JKExamLibrary)
Total work = 14 × 18 = 252 man-days. Required days = 252/18 = 14.0 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can complete a work in 18 days and B can complete the same work in 33 days. If they work together, in how many days will the work be completed?
A. 17.65
B. 11.65
C. 13.65
D. 15.65

Correct Answer: Option B


Explanation:
Combined rate = 1/18 + 1/33. Time = 1 ÷ combined rate = 11.65 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A and B can do a piece of work in 10 days, B and C in 12 days, and C and A in 15 days. How long will C alone take to complete the work?
A. 40 days
B. 24 days
C. 30 days
D. 60 days

Correct Answer: Option A


Explanation:
Total work = LCM(10, 12, 15) = 60 units. Efficiency of (A+B) = 6, (B+C) = 5, (C+A) = 4. Summing gives 2*(A+B+C) = 15 => Efficiency of (A+B+C) = 7.5. Efficiency of C = (A+B+C) - (A+B) = 7.5 - 6 = 1.5. Time taken by C alone = 60 / 1.5 = 40 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
19 men can complete a work in 29 days. If 23 men work at the same rate, in how many days will the work be completed?
A. 27.96
B. 29.96
C. 25.96
D. 23.96

Correct Answer: Option D


Explanation:
Total work = 19 × 29 = 551 man-days. Required days = 551/23 = 23.96 days.

This question belongs to: Maths Time and Work