22 men can complete a work in 14 days. If 27 men work at the same rate, the work will be completed in: MCQ with Answer and Explanation

22 men can complete a work in 14 days. If 27 men work at the same rate, the work will be completed in:
A. 21.41
B. 26.41
C. 16.41
D. 11.41
Answer: Option D
Solution (By JKExamLibrary)
Total work = 308 man-days. Time = 308/27 = 11.41 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can build a wall in 20 days, while B can destroy it in 30 days. If they work on alternate days starting with A, in how many days will the wall be completely built?
A. 116 days
B. 115 days
C. 120 days
D. 113 days

Correct Answer: Option B


Explanation:
Total work = LCM(20, 30) = 60 units. Efficiency of A = +3, B = -2. In 2 days (A then B), net work done = 3 - 2 = 1 unit. We need to reach 60 units. Since A can add 3 units on his turn, we find when work reaches 60 - 3 = 57 units. 57 units will be done in 57 * 2 = 114 days. On the 115th day, A works and completes 3 units, making the total work 57 + 3 = 60 units. So, the wall is built in 115 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:
A. 4 days
B. 5 days
C. 7 days
D. 6 days

Correct Answer: Option A


Explanation:
Total work = 10 * (6M + 8B) = 2 * (26M + 48B) => 60M + 80B = 52M + 96B => 8M = 16B => 1M = 2B. Total work in terms of boys = 10 * (6*2B + 8B) = 10 * 20B = 200 boy-days. Efficiency of 15 men and 20 boys = 15*2B + 20B = 50B. Time taken = 200 / 50 = 4 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can complete a work in 14 days and B in 15 days. If they work together, the work will be completed in:
A. 7.24
B. 12.24
C. 17.24
D. 22.24

Correct Answer: Option A


Explanation:
Combined rate = 1/14 + 1/15. Required time = 7.24 days.

This question belongs to: Maths Time and Work