A and B can complete a work in 12 days and 16 days respectively. Both work together for 3 days and then A leaves. How long will B take to complete the remaining work? MCQ with Answer and Explanation

A and B can complete a work in 12 days and 16 days respectively. Both work together for 3 days and then A leaves. How long will B take to complete the remaining work?
A. 9 days
B. 8 days
C. 11 days
D. 10 days
Answer: Option A
Solution (By JKExamLibrary)
Total work = LCM(12, 16) = 48 units. Efficiency of A = 4, B = 3. Combined efficiency = 7 units/day. In 3 days, work completed = 3 * 7 = 21 units. Remaining work = 48 - 21 = 27 units. Time taken by B to complete remaining work = 27 / 3 = 9 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
20 men can complete a work in 22 days. If 25 men work at the same rate, the work will be completed in:
A. 22.6
B. 32.6
C. 27.6
D. 17.6

Correct Answer: Option D


Explanation:
Total work = 440 man-days. Time = 440/25 = 17.6 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a work in 23 days and B in 23 days. If they work together, the work will be completed in:
A. 26.5
B. 11.5
C. 21.5
D. 16.5

Correct Answer: Option B


Explanation:
Combined rate = 1/23 + 1/23. Required time = 11.5 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can complete a work in 18 days and B in 16 days. If they work together, the work will be completed in:
A. 13.47
B. 18.47
C. 8.47
D. 23.47

Correct Answer: Option C


Explanation:
Combined rate = 1/18 + 1/16. Required time = 8.47 days.