A and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. In how many days can A alone complete the work? MCQ with Answer and Explanation
Explanation:
Total work = LCM(15, 20) = 60 units. Efficiency of A = 4, B = 3. Combined efficiency = 7. In 6 days, work done = 6 * 7 = 42 units. Remaining work = 60 - 42 = 18 units. Time taken by A to complete remaining work = 18 / 4 = 4.5 days.
A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. Find the original number of workers.
Explanation:
Let the original number of workers be x. Using M1 * D1 = M2 * D2: x * 100 = (x - 10) * 110 => 100x = 110x - 1100 => 10x = 1100 => x = 110.
No comments yet. Be the first to start the discussion!