A can complete a piece of work in 12 days, and B can complete the same work in 24 days. If they work together, how many days will it take them to complete the work? MCQ with Answer and Explanation

A can complete a piece of work in 12 days, and B can complete the same work in 24 days. If they work together, how many days will it take them to complete the work?
A. 10 days
B. 8 days
C. 6 days
D. 14 days
Answer: Option B
Solution (By JKExamLibrary)
A's 1-day work = 1/12, B's 1-day work = 1/24. Combined 1-day work = 1/12 + 1/24 = 3/24 = 1/8. Therefore, they will complete the work together in 8 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can do a work in 18 days and B in 24 days. They start together but A leaves 3 days before the completion of the work. Find the total number of days taken to complete the work.
A. 12 days
B. 10 days
C. 11 days
D. 13 days

Correct Answer: Option A


Explanation:
Total work = LCM(18, 24) = 72 units. Efficiency of A = 4, B = 3. Let total days be x. A works for (x - 3) days, B works for x days. 4(x - 3) + 3x = 72 => 4x - 12 + 3x = 72 => 7x = 84 => x = 12 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a work in 17 days and B in 44 days. If both work together, in how many days will the work be completed?
A. 17.26
B. 19.76
C. 14.76
D. 12.26

Correct Answer: Option D


Explanation:
Combined rate = 1/17 + 1/44. Time = 12.26 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
33 men can complete a work in 26 days. If 41 men work at the same rate, how many days are required?
A. 25.93
B. 20.93
C. 23.43
D. 28.43

Correct Answer: Option B


Explanation:
Total work = 858 man-days. Days = 20.93.

This question belongs to: Maths Time and Work