A can complete a piece of work in 12 days and B in 15 days. They work together for 3 days and then B leaves. In how many days will A complete the remaining work? MCQ with Answer and Explanation

A can complete a piece of work in 12 days and B in 15 days. They work together for 3 days and then B leaves. In how many days will A complete the remaining work?
A. 5.6 days
B. 4.8 days
C. 7.5 days
D. 6.6 days
Answer: Option D
Solution (By JKExamLibrary)
Total work = LCM(12, 15) = 60 units. Efficiency of A = 5, B = 4. Combined efficiency = 9 units/day. In 3 days, work completed = 3 * 9 = 27 units. Remaining work = 60 - 27 = 33 units. Time taken by A to complete remaining work = 33 / 5 = 6.6 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
11 men can complete a work in 15 days. If 15 men work at the same rate, in how many days will the work be completed?
A. 11.0
B. 15.0
C. 13.0
D. 17.0

Correct Answer: Option A


Explanation:
Total work = 11 × 15 = 165 man-days. Required days = 165/15 = 11.0 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a work in 22 days and B in 44 days. After working together for 5 days, what percentage of work remains?
A. 73.41
B. 65.91
C. 70.91
D. 68.41

Correct Answer: Option B


Explanation:
Remaining work = (1 - 5*(1/22+1/44))×100 = 65.91%.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can complete a piece of work in 10 days, B in 15 days, and C in 20 days. A and C worked together for 2 days and then A was replaced by B. In how many days altogether was the work completed?
A. 8 days
B. 9 days
C. 7 days
D. 6 days

Correct Answer: Option A


Explanation:
Total work = LCM(10, 15, 20) = 60 units. Efficiency of A = 6, B = 4, C = 3. A and C work for 2 days: work done = 2 * (6 + 3) = 18 units. Remaining work = 60 - 18 = 42 units. B and C complete remaining work together with efficiency = 4 + 3 = 7 units/day. Time taken for remaining work = 42 / 7 = 6 days. Total time = 2 + 6 = 8 days.

This question belongs to: Maths Time and Work