A can complete a piece of work in 12 days and B in 15 days. They work together for 3 days and then B leaves. In how many days will A complete the remaining work? MCQ with Answer and Explanation
A can complete a piece of work in 12 days and B in 15 days. They work together for 3 days and then B leaves. In how many days will A complete the remaining work?
A. 5.6 days
B. 4.8 days
C. 7.5 days
D. 6.6 days
Answer: Option D
Solution (By JKExamLibrary)
Total work = LCM(12, 15) = 60 units. Efficiency of A = 5, B = 4. Combined efficiency = 9 units/day. In 3 days, work completed = 3 * 9 = 27 units. Remaining work = 60 - 27 = 33 units. Time taken by A to complete remaining work = 33 / 5 = 6.6 days.
A can complete a piece of work in 10 days, B in 15 days, and C in 20 days. A and C worked together for 2 days and then A was replaced by B. In how many days altogether was the work completed?
Explanation:
Total work = LCM(10, 15, 20) = 60 units. Efficiency of A = 6, B = 4, C = 3. A and C work for 2 days: work done = 2 * (6 + 3) = 18 units. Remaining work = 60 - 18 = 42 units. B and C complete remaining work together with efficiency = 4 + 3 = 7 units/day. Time taken for remaining work = 42 / 7 = 6 days. Total time = 2 + 6 = 8 days.
No comments yet. Be the first to start the discussion!