A can complete a work in 12 days and B in 25 days. If they work together, the work will be completed in: MCQ with Answer and Explanation

A can complete a work in 12 days and B in 25 days. If they work together, the work will be completed in:
A. 13.11
B. 18.11
C. 23.11
D. 8.11
Answer: Option D
Solution (By JKExamLibrary)
Combined rate = 1/12 + 1/25. Required time = 8.11 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can do a piece of work in 80 days. He works at it for 10 days and then B alone finishes the remaining work in 42 days. In how many days can A and B together complete the work?
A. 35 days
B. 25 days
C. 24 days
D. 30 days

Correct Answer: Option D


Explanation:
Let total work be 80 units. Efficiency of A = 1 unit/day. In 10 days, A completes 10 units. Remaining work = 80 - 10 = 70 units. B finishes 70 units in 42 days, so B's efficiency = 70 / 42 = 5/3 units/day. Combined efficiency of A and B = 1 + 5/3 = 8/3 units/day. Time taken together = 80 / (8/3) = (80 * 3) / 8 = 30 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a work in 13 days and B can complete the same work in 28 days. If they work together, in how many days will the work be completed?
A. 14.88
B. 12.88
C. 8.88
D. 10.88

Correct Answer: Option C


Explanation:
Combined rate = 1/13 + 1/28. Time = 1 รท combined rate = 8.88 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can build a wall in 20 days, while B can destroy it in 30 days. If they work on alternate days starting with A, in how many days will the wall be completely built?
A. 116 days
B. 113 days
C. 120 days
D. 115 days

Correct Answer: Option D


Explanation:
Total work = LCM(20, 30) = 60 units. Efficiency of A = +3, B = -2. In 2 days (A then B), net work done = 3 - 2 = 1 unit. We need to reach 60 units. Since A can add 3 units on his turn, we find when work reaches 60 - 3 = 57 units. 57 units will be done in 57 * 2 = 114 days. On the 115th day, A works and completes 3 units, making the total work 57 + 3 = 60 units. So, the wall is built in 115 days.

This question belongs to: Maths Time and Work