A can do a piece of work in 80 days. He works at it for 10 days and then B alone finishes the remaining work in 42 days. In how many days can A and B together complete the work? MCQ with Answer and Explanation

A can do a piece of work in 80 days. He works at it for 10 days and then B alone finishes the remaining work in 42 days. In how many days can A and B together complete the work?
A. 30 days
B. 24 days
C. 25 days
D. 35 days
Answer: Option A
Solution (By JKExamLibrary)
Let total work be 80 units. Efficiency of A = 1 unit/day. In 10 days, A completes 10 units. Remaining work = 80 - 10 = 70 units. B finishes 70 units in 42 days, so B's efficiency = 70 / 42 = 5/3 units/day. Combined efficiency of A and B = 1 + 5/3 = 8/3 units/day. Time taken together = 80 / (8/3) = (80 * 3) / 8 = 30 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can do a work in 11 days and B in 17 days. In how many days will they complete 75% of the work together?
A. 5.01
B. 12.51
C. 10.01
D. 7.51

Correct Answer: Option A


Explanation:
Combined time for full work multiplied by 0.75 = 5.01 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a work in 17 days and B in 22 days. If both work together, in how many days will the work be completed?
A. 12.09
B. 17.09
C. 14.59
D. 9.59

Correct Answer: Option D


Explanation:
Combined rate = 1/17 + 1/22. Time = 9.59 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A is twice as efficient as B and can finish a job in 20 days less than B. In how many days can they complete the work together?
A. 14(2/3) days
B. 12 days
C. 15 days
D. 13(1/3) days

Correct Answer: Option D


Explanation:
Efficiency ratio A : B = 2 : 1. Time ratio A : B = 1 : 2. Difference = 1 part = 20 days. So A takes 20 days and B takes 40 days. Total work = 40 units. Combined efficiency = 3. Time taken together = 40 / 3 = 13(1/3) days.

This question belongs to: Maths Time and Work