A can complete a work in 19 days and B in 22 days. If they work together, the work will be completed in: MCQ with Answer and Explanation

A can complete a work in 19 days and B in 22 days. If they work together, the work will be completed in:
A. 20.2
B. 25.2
C. 15.2
D. 10.2
Answer: Option D
Solution (By JKExamLibrary)
Combined rate = 1/19 + 1/22. Required time = 10.2 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
X can do a piece of work in 40 days. He works at it for 8 days and then Y alone finishes the remaining work in 16 days. How long will X and Y together take to complete the work?
A. 15 days
B. 16 days
C. 13(1/3) days
D. 14 days

Correct Answer: Option C


Explanation:
Let total work be 40 units. Efficiency of X = 1 unit/day. In 8 days, X completes 8 units. Remaining work = 40 - 8 = 32 units. Y finishes 32 units in 16 days, so Y's efficiency = 32 / 16 = 2 units/day. Combined efficiency of X and Y = 1 + 2 = 3 units/day. Time taken together = 40 / 3 = 13(1/3) days.

This question belongs to: Maths Time and Work
Question #2 Report Error
Two workers A and B are engaged to do a piece of work. Working together they would take 8 hours less than the time taken by A alone, and 4.5 hours less than the time taken by B alone. Find the time they take to complete the work together.
A. 5 hours
B. 6 hours
C. 8 hours
D. 7 hours

Correct Answer: Option B


Explanation:
Let the time taken together be t hours. Then A takes (t + 8) hours and B takes (t + 4.5) hours. Using the direct formula for such problems: t = sqrt(a * b), where a and b are the extra times. t = sqrt(8 * 4.5) = sqrt(36) = 6 hours.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can complete a work in 14 days and B can complete the same work in 19 days. If they work together, in how many days will the work be completed?
A. 8.06
B. 14.06
C. 10.06
D. 12.06

Correct Answer: Option A


Explanation:
Combined rate = 1/14 + 1/19. Time = 1 รท combined rate = 8.06 days.

This question belongs to: Maths Time and Work