A can do a piece of work in 10 days, B in 12 days and C in 15 days. They carry out the work together and get a total of Rs. 4500 as wages. Find the share of C. MCQ with Answer and Explanation

A can do a piece of work in 10 days, B in 12 days and C in 15 days. They carry out the work together and get a total of Rs. 4500 as wages. Find the share of C.
A. Rs. 1200
B. Rs. 1500
C. Rs. 1000
D. Rs. 1800
Answer: Option A
Solution (By JKExamLibrary)
Total work = LCM(10, 12, 15) = 60 units. Efficiency of A = 6, B = 5, C = 4. Ratio of wages = 6 : 5 : 4. Total ratio parts = 15. Share of C = (4 / 15) * 4500 = 4 * 300 = Rs. 1200.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
15 men can complete a work in 22 days. If 20 men work at the same rate, the work will be completed in:
A. 31.5
B. 21.5
C. 26.5
D. 16.5

Correct Answer: Option D


Explanation:
Total work = 330 man-days. Time = 330/20 = 16.5 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a work in 15 days and B can complete the same work in 30 days. If they work together, in how many days will the work be completed?
A. 16.0
B. 12.0
C. 10.0
D. 14.0

Correct Answer: Option C


Explanation:
Combined rate = 1/15 + 1/30. Time = 1 ÷ combined rate = 10.0 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:
A. 6 days
B. 4 days
C. 7 days
D. 5 days

Correct Answer: Option B


Explanation:
Total work = 10 * (6M + 8B) = 2 * (26M + 48B) => 60M + 80B = 52M + 96B => 8M = 16B => 1M = 2B. Total work in terms of boys = 10 * (6*2B + 8B) = 10 * 20B = 200 boy-days. Efficiency of 15 men and 20 boys = 15*2B + 20B = 50B. Time taken = 200 / 50 = 4 days.

This question belongs to: Maths Time and Work