A can do a piece of work in 15 days and B in 20 days. They began the work together but A left after 4 days. In how many days will B complete the remaining work? MCQ with Answer and Explanation

A can do a piece of work in 15 days and B in 20 days. They began the work together but A left after 4 days. In how many days will B complete the remaining work?
A. 8 days
B. 10(1/3) days
C. 9(1/3) days
D. 10(2/3) days
Answer: Option D
Solution (By JKExamLibrary)
Total work = LCM(15, 20) = 60 units. Efficiency of A = 4, B = 3. Combined efficiency = 7. In 4 days, work completed = 4 * 7 = 28 units. Remaining work = 60 - 28 = 32 units. Time taken by B to complete remaining work = 32 / 3 = 10(2/3) days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A left after some days and B finished the remaining work in 23 days. After how many days did A leave?
A. 6 days
B. 8 days
C. 9 days
D. 12 days

Correct Answer: Option C


Explanation:
Total work = LCM(45, 40) = 360 units. Efficiency of A = 8, B = 9. B worked alone for 23 days: work done = 23 * 9 = 207 units. Remaining work = 360 - 207 = 153 units. This was done by A and B together. Combined efficiency = 8 + 9 = 17. Number of days they worked together = 153 / 17 = 9 days. Thus, A left after 9 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can do a work in 9 days and B in 17 days. In how many days will they complete 75% of the work together?
A. 6.91
B. 9.41
C. 4.41
D. 11.91

Correct Answer: Option C


Explanation:
Combined time for full work multiplied by 0.75 = 4.41 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
14 men can complete a work in 24 days. If 18 men work at the same rate, in how many days will the work be completed?
A. 22.67
B. 18.67
C. 24.67
D. 20.67

Correct Answer: Option B


Explanation:
Total work = 14 × 24 = 336 man-days. Required days = 336/18 = 18.67 days.

This question belongs to: Maths Time and Work