A and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A left after some days and B finished the remaining work in 23 days. After how many days did A leave? MCQ with Answer and Explanation

A and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A left after some days and B finished the remaining work in 23 days. After how many days did A leave?
A. 12 days
B. 8 days
C. 6 days
D. 9 days
Answer: Option D
Solution (By JKExamLibrary)
Total work = LCM(45, 40) = 360 units. Efficiency of A = 8, B = 9. B worked alone for 23 days: work done = 23 * 9 = 207 units. Remaining work = 360 - 207 = 153 units. This was done by A and B together. Combined efficiency = 8 + 9 = 17. Number of days they worked together = 153 / 17 = 9 days. Thus, A left after 9 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can do a piece of work in 40 days. He works at it for 8 days and then B finishes it in 16 days. How long will A and B together take to complete the work?
A. 15 days
B. 25 days
C. 20 days
D. 13(1/3) days

Correct Answer: Option D


Explanation:
Let total work be 40 units. Efficiency of A = 1 unit/day. In 8 days, A completes 8 units. Remaining work = 40 - 8 = 32 units. B finishes 32 units in 16 days, so B's efficiency = 32 / 16 = 2 units/day. Combined efficiency of A and B = 1 + 2 = 3 units/day. Time taken together = 40 / 3 = 13(1/3) days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a work in 16 days and B in 20 days. If both work together, in how many days will the work be completed?
A. 8.89
B. 16.39
C. 13.89
D. 11.39

Correct Answer: Option A


Explanation:
Combined rate = 1/16 + 1/20. Time = 8.89 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A and B can complete a work in 12 days and 16 days respectively. Both work together for 3 days and then A leaves. How long will B take to complete the remaining work?
A. 8 days
B. 10 days
C. 9 days
D. 11 days

Correct Answer: Option C


Explanation:
Total work = LCM(12, 16) = 48 units. Efficiency of A = 4, B = 3. Combined efficiency = 7 units/day. In 3 days, work completed = 3 * 7 = 21 units. Remaining work = 48 - 21 = 27 units. Time taken by B to complete remaining work = 27 / 3 = 9 days.

This question belongs to: Maths Time and Work