A can do a piece of work in 80 days. He works at it for 10 days and then B alone finishes the remaining work in 42 days. In how many days will A and B together complete the work? MCQ with Answer and Explanation
A can do a piece of work in 80 days. He works at it for 10 days and then B alone finishes the remaining work in 42 days. In how many days will A and B together complete the work?
A. 30 days
B. 35 days
C. 25 days
D. 24 days
Answer: Option A
Solution (By JKExamLibrary)
A's 10-day work = 10/80 = 1/8. Remaining work = 7/8. B completes 7/8 work in 42 days, so B completes full work in 42 * (8/7) = 48 days. Combined 1-day work = 1/80 + 1/48 = (3 + 5)/240 = 8/240 = 1/30. They finish together in 30 days.
Explanation:
Total work = LCM(4, 5, 10) = 20 units. Efficiency of A = 5, B = 4, C = 2. Combined efficiency = 5 + 4 + 2 = 11 units/day. Time taken together = 20 / 11 = 1(9/11) days.
Explanation:
2(A + B + C)'s 1-day work = 1/12 + 1/15 + 1/20 = 12/60 = 1/5. Therefore, (A + B + C)'s 1-day work = 1/10. Working together, they finish in 10 days.
No comments yet. Be the first to start the discussion!