A can do a piece of work in 80 days. He works at it for 10 days and then B alone finishes the remaining work in 42 days. In how many days will A and B together complete the work? MCQ with Answer and Explanation

A can do a piece of work in 80 days. He works at it for 10 days and then B alone finishes the remaining work in 42 days. In how many days will A and B together complete the work?
A. 30 days
B. 35 days
C. 25 days
D. 24 days
Answer: Option A
Solution (By JKExamLibrary)
A's 10-day work = 10/80 = 1/8. Remaining work = 7/8. B completes 7/8 work in 42 days, so B completes full work in 42 * (8/7) = 48 days. Combined 1-day work = 1/80 + 1/48 = (3 + 5)/240 = 8/240 = 1/30. They finish together in 30 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can do a work in 4 days, B in 5 days and C in 10 days. Find the time taken by A, B and C together to do the work.
A. 2(1/11) days
B. 2 days
C. 1(9/11) days
D. 1(7/11) days

Correct Answer: Option C


Explanation:
Total work = LCM(4, 5, 10) = 20 units. Efficiency of A = 5, B = 4, C = 2. Combined efficiency = 5 + 4 + 2 = 11 units/day. Time taken together = 20 / 11 = 1(9/11) days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a work in 29 days and B in 34 days. If both work together, in how many days will the work be completed?
A. 18.15
B. 20.65
C. 23.15
D. 15.65

Correct Answer: Option D


Explanation:
Combined rate = 1/29 + 1/34. Time = 15.65 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A and B can do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days. In how many days will A, B, and C finish it working together?
A. 8 days
B. 12 days
C. 10 days
D. 5 days

Correct Answer: Option C


Explanation:
2(A + B + C)'s 1-day work = 1/12 + 1/15 + 1/20 = 12/60 = 1/5. Therefore, (A + B + C)'s 1-day work = 1/10. Working together, they finish in 10 days.

This question belongs to: Maths Time and Work