A can do a work in 4 days, B in 5 days and C in 10 days. Find the time taken by A, B and C together to do the work.
A. 2 days
B. 1(7/11) days
C. 1(9/11) days
D. 2(1/11) days
Answer: Option C
Solution (By JKExamLibrary)
Total work = LCM(4, 5, 10) = 20 units. Efficiency of A = 5, B = 4, C = 2. Combined efficiency = 5 + 4 + 2 = 11 units/day. Time taken together = 20 / 11 = 1(9/11) days.