A can do a work in 19 days and B in 23 days. In how many days will they complete 75% of the work together? MCQ with Answer and Explanation

A can do a work in 19 days and B in 23 days. In how many days will they complete 75% of the work together?
A. 12.8
B. 7.8
C. 15.3
D. 10.3
Answer: Option B
Solution (By JKExamLibrary)
Combined time for full work multiplied by 0.75 = 7.8 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can build a wall in 30 days, while B can destroy it in 40 days. If they work on alternate days starting with A, in how many days will the wall be built?
A. 240 days
B. 233 days
C. 235 days
D. 237 days

Correct Answer: Option B


Explanation:
Total work = LCM(30, 40) = 120 units. Efficiency of A = +4, B = -3. In 2 days, net work = 4 - 3 = 1 unit. We look for when the work reaches 120 - 4 = 116 units. 116 units are done in 116 * 2 = 232 days. On the 233rd day, A works and completes 4 units, making total work 116 + 4 = 120 units. Thus, the wall is completed in 233 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a work in 31 days and B in 24 days. If both work together, in how many days will the work be completed?
A. 21.03
B. 13.53
C. 16.03
D. 18.53

Correct Answer: Option B


Explanation:
Combined rate = 1/31 + 1/24. Time = 13.53 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can do a work in 9 days and B in 23 days. In how many days will they complete 75% of the work together?
A. 4.85
B. 9.85
C. 12.35
D. 7.35

Correct Answer: Option A


Explanation:
Combined time for full work multiplied by 0.75 = 4.85 days.

This question belongs to: Maths Time and Work