A can build a wall in 30 days, while B can destroy it in 40 days. If they work on alternate days starting with A, in how many days will the wall be built? MCQ with Answer and Explanation

A can build a wall in 30 days, while B can destroy it in 40 days. If they work on alternate days starting with A, in how many days will the wall be built?
A. 233 days
B. 235 days
C. 240 days
D. 237 days
Answer: Option A
Solution (By JKExamLibrary)
Total work = LCM(30, 40) = 120 units. Efficiency of A = +4, B = -3. In 2 days, net work = 4 - 3 = 1 unit. We look for when the work reaches 120 - 4 = 116 units. 116 units are done in 116 * 2 = 232 days. On the 233rd day, A works and completes 4 units, making total work 116 + 4 = 120 units. Thus, the wall is completed in 233 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can complete a work in 15 days and B in 32 days. If both work together, in how many days will the work be completed?
A. 15.21
B. 12.71
C. 10.21
D. 17.71

Correct Answer: Option C


Explanation:
Combined rate = 1/15 + 1/32. Time = 10.21 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?
A. 45 days
B. 50 days
C. 40 days
D. 35 days

Correct Answer: Option C


Explanation:
Total work = 8 * (4M + 6W) = 10 * (3M + 7W) => 32M + 48W = 30M + 70W => 2M = 22W => 1M = 11W. Total work in terms of women = 8 * (4*11W + 6W) = 8 * 50W = 400 W-days. Time taken by 10 women = 400 / 10 = 40 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can complete a work in 16 days and B can complete the same work in 31 days. If they work together, in how many days will the work be completed?
A. 14.55
B. 12.55
C. 16.55
D. 10.55

Correct Answer: Option D


Explanation:
Combined rate = 1/16 + 1/31. Time = 1 ÷ combined rate = 10.55 days.

This question belongs to: Maths Time and Work