If 6 men and 8 boys can do a piece of work in 10 days, then 3 men and 4 boys will do the same work in: MCQ with Answer and Explanation

If 6 men and 8 boys can do a piece of work in 10 days, then 3 men and 4 boys will do the same work in:
A. 12 days
B. 20 days
C. 5 days
D. 15 days
Answer: Option B
Solution (By JKExamLibrary)
The number of workers (3 men and 4 boys) is exactly half of the original group (6 men and 8 boys). Since efficiency becomes half, the time taken will double. Total time = 10 * 2 = 20 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can complete a work in 17 days and B can complete the same work in 17 days. If they work together, in how many days will the work be completed?
A. 10.5
B. 14.5
C. 8.5
D. 12.5

Correct Answer: Option C


Explanation:
Combined rate = 1/17 + 1/17. Time = 1 ÷ combined rate = 8.5 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
23 men can complete a work in 30 days. If 28 men work at the same rate, the work will be completed in:
A. 34.64
B. 39.64
C. 29.64
D. 24.64

Correct Answer: Option D


Explanation:
Total work = 690 man-days. Time = 690/28 = 24.64 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A, B and C can do a piece of work in 20, 30 and 60 days respectively. If A works everyday and is assisted by B and C together on every third day, then in how many days will the work be completed?
A. 18 days
B. 20 days
C. 12 days
D. 15 days

Correct Answer: Option D


Explanation:
Total work = LCM(20, 30, 60) = 60 units. Efficiency of A = 3, B = 2, C = 1. Day 1: A works = 3 units. Day 2: A works = 3 units. Day 3: A+B+C work = 3 + 2 + 1 = 6 units. Work done in 3 days = 3 + 3 + 6 = 12 units. Number of 3-day cycles to complete 60 units = 60 / 12 = 5 cycles. Total days = 5 * 3 = 15 days.

This question belongs to: Maths Time and Work