12 men can complete a work in 22 days. If 16 men work at the same rate, in how many days will the work be completed? MCQ with Answer and Explanation

12 men can complete a work in 22 days. If 16 men work at the same rate, in how many days will the work be completed?
A. 22.5
B. 16.5
C. 20.5
D. 18.5
Answer: Option B
Solution (By JKExamLibrary)
Total work = 12 × 22 = 264 man-days. Required days = 264/16 = 16.5 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can do a piece of work in 20 days and B in 30 days. They work together for some time and then B leaves. If A completes the remaining work in 5 days, for how many days did they work together?
A. 8 days
B. 10 days
C. 9 days
D. 6 days

Correct Answer: Option C


Explanation:
Total work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. A worked alone for 5 days: work done = 5 * 3 = 15 units. Remaining work = 60 - 15 = 45 units. This was completed by A and B together. Combined efficiency = 3 + 2 = 5 units/day. Number of days they worked together = 45 / 5 = 9 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can do a piece of work in 80 days. He works at it for 10 days and then B alone finishes the remaining work in 42 days. In how many days will A and B together complete the work?
A. 24 days
B. 35 days
C. 30 days
D. 25 days

Correct Answer: Option C


Explanation:
A's 10-day work = 10/80 = 1/8. Remaining work = 7/8. B completes 7/8 work in 42 days, so B completes full work in 42 * (8/7) = 48 days. Combined 1-day work = 1/80 + 1/48 = (3 + 5)/240 = 8/240 = 1/30. They finish together in 30 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can complete a work in 22 days and B in 44 days. After working together for 5 days, what percentage of work remains?
A. 68.41
B. 65.91
C. 73.41
D. 70.91

Correct Answer: Option B


Explanation:
Remaining work = (1 - 5*(1/22+1/44))×100 = 65.91%.

This question belongs to: Maths Time and Work